Development of a stacking frame system

Our main challenge was to develop a stacking frame system for the blades as they were not initially planned to be stacked by our client SGRE (Siemens Gamesa Renewables). Luckily, we had an amazing team of experts at our side from SAL Engineering.

Fabian Obert, Manager Chartering & Projects at Jumbo-SAL-Alliance

Development of a stacking frame system
ClientSiemens Gamesa Renewable Energy A/S
Cargo
  • B81 blades (82.07 × 7.3 × 6.08 m, 44.3 mt)
  • 8MW Nacelle (20 × 7.9 × 10.58 m, 392.5 mt)
POL
  • Esbjerg, Denmark
  • Aalborg, Denmark
POD
  • Taichung, Taiwan
Engineering scope
  • Development of a stacking frame system
Methods / Software
  • AutoCAD
  • RFEM
  • Ansys
  • Inventor

Our solutions

  • Development of a stacking frame system

  • Conducting FEM (Finite Element Method) analyses of the SAL vessel weather decks

  • Creation of an intake of 15 blades on deck while still being able to load and discharge the cargo with own gear and without shore crane assistance

  • Special weight spreading arrangement on the weather deck to transfer loads from the blade stacks into the deck and hull

  • Supervising the manufacturing of the stacking frames

  • Delivery arrangement of finished frames into port of loading

  • Modification of clients’ rigging arrangements as shorter rigging was required due to the limited hook height

  • Special working at heights training for all crew members, as hook height maximum was reached for all blades in the top layer of the stacking frames

  • Discharging operations at three different terminals in Taiwan

Read the full story

A GREEN REVOLUTION  FOR TAIWAN

Development of a stacking frame system for 15 blades on deck

Taiwan is in the middle of a green energy revolution. The Formosa wind farms have placed the country at the centre of Asia’s growing offshore wind market and are playing a key role in realizing Taiwan’s green energy ambitions. In addition, the Yunlin offshore wind farm and the greater Changhua offshore wind farms are major milestones in Taiwan’s aim to reduce greenhouse gas emissions by 50% in 2050 and increase the share of renewable energy in its power supply to 20% by 2025.

The Jumbo-SAL-Alliance went full steam ahead to support a greener future in Taiwan. The task of moving 75 8-MW SG 8.0-167 DD turbines and 225 blades from Cuxhaven (Germany), Esbjerg and Aalborg (Denmark) to Taichung (Taiwan) kept the type 176, type 171, type 116 and type 161B vessels busy for quite some time. “Having this many vessels involved was not even the most difficult part of this project,” explained Fabian Obert, Manager Chartering & Projects at Jumbo-SAL-Alliance. “Our main challenge was to develop a stacking frame system for the blades as they were not initially planned to be stacked by our client SGRE (Siemens Gamesa Renewables). Luckily, we had an amazing team of experts at our side from SAL Engineering.”

Let the stacking games begin

It was necessary to develop a new stacking system to fulfil the client’s needs and safely transport the blades to their final destinations. “We usually like to use a mezzanine deck as a solution for projects of this kind, but this time it did not create sufficient intake. The aim was to create an intake of 15 blades on deck while still being able to load and discharge the cargo with our own gear and without shore crane assistance,” said Jonas Wehling, Project Engineer & Naval Architect at SAL Engineering.

In the end, SAL Engineering developed a stacking frame system that perfectly meets the client’s demands, including conducting FEM (Finite Element Method) analyses of the SAL vessel weather decks and supervising the manufacturing of the stacking frames. “Last but not least, we also arranged the delivery of the finished frames into the port of loading in Aalborg, Denmark,” added Jonas Wehling.

Three in one

There was another more operational challenge involved in the project: Discharging operations took place at three different terminals in Taiwan, as the cargo counted units for different project sites. Fabian Obert emphasised: “Handling the blades, measuring 82.07 × 7.3 × 6.08 metres and weighing 44.3 tons each, was quite difficult, as we had to operate in heights of up to 24 metres above deck.” He continued: “We loaded and discharged the cargo with our own gear and cranes. As a result, the hook height maximum was reached for all blades in the top layer of the stacking frames. Keeping this in mind, we had all crew members participate in special working at heights training to ensure safety and efficiency.”

All blades were discharged using the vessel’s cranes in a tandem lift with extremely limited clearance between the blades. “We also had to modify our clients’ rigging arrangements to make it work as shorter rigging was required due to the limited hook height,” said Project Engineer, Jonas Wehling. He added: “The blades were lashed with standard lashing for the sea passage, but a careful weight spreading arrangement was needed on the weather deck to transfer loads from the blade stacks into the deck and hull.”

The first blades and nacelles safely arrived in their project ports in Taiwan and are waiting to be commissioned offshore at the Formosa, Yunlin and Greater Changhua project sites. The shipments will likely continue until mid-2022. “With this project, we once again saw that SAL Engineering will find just the right solution for even the most unique requests. Being part of these milestone projects makes us very proud, and we look forward to delivering logistics services for many more green projects to come,” Fabian Obert and Jonas Wehling agreed.

Collapse story

More references

26 metre lifting beams

Two shiploaders

Fork lift of shiploaders using two 26 metre lifting beams

Read more

Huge trailer front set on rails

Partly assembled shiploaders

Transport and installation

Read more

Special hang-off frames 

Replacing riser plates on FPSO

Offshore feeding and double banking in DP mode

Read more

A customized Lifting Tool

Horns Rev 3

Upright transportation of 49 Transition Pieces (TPs)

Read more

A Ballast Procedure for 15 tanks

Buoy Barging

Planning and supervision of shifting buoys into/out of water

Read more